Lotus Factory 3 Project

Contract Value approx. £923,000.00

Project Details

The existing Factory 3 building was originally an aircraft hangar and more recently just storage space. To increase production space the hangar was stripped back to the bare steel and completely refurbished with the addition of a mezzanine floor. The works involved a completely new Mechanical and Electrical installation which comprised of the following:-

 

  • Detailed M&E design
  • General and Emergency Lighting
  • External lighting
  • General purpose power
  • HV infrastructure upgrade
  • Switchgear & containment
  • Fire Alarm System
  • Data installation
  • Compressed Air
  • Vacuum
  • BMS
  • Gas infrastructure upgrade
  • Ventilation
  • Hot and cold water supplies
  • Heating installation
  • Above ground drainage